OEE Calculator – Overall Equipment Effectiveness
Calculate Availability, Performance and Quality. See your OEE score — and exactly how much production capacity you're losing in ₹ per month.
💰 Production Loss in ₹ (optional)
📊 OEE Breakdown
Focus your improvement effort here first — it will have the most impact on OEE.
💸 Production Loss (₹)
OEE Formula
OEE Benchmarks
| OEE % | Rating | Status |
|---|---|---|
| < 65% | Poor | ❌ Significant losses |
| 65–75% | Average | ⚠️ Room to improve |
| 75–85% | Good | ✅ Above average |
| > 85% | World Class | 🏆 Excellent |
Understanding Your OEE Score
A single OEE number hides where you're losing capacity. Two factories can both score 60% OEE with completely different problems. One has poor Availability (constant breakdowns), the other has poor Performance (machine running slowly). The fix for each is entirely different — and without looking at all three components, you'll chase the wrong solution.
The Six Big Losses in OEE
OEE is designed to identify and quantify the Six Big Losses — the six ways production time is wasted. Every loss maps to one of the three OEE components:
| # | Loss Type | OEE Component | Example | Typical Impact |
|---|---|---|---|---|
| 1 | Equipment Failure / Breakdown | Availability ↓ | Motor trips, belt breaks, hydraulic failure | 5–15% Availability loss |
| 2 | Setup & Adjustments (Changeover) | Availability ↓ | Mould change, size change, product changeover | 3–10% Availability loss |
| 3 | Idling & Minor Stops | Performance ↓ | Material jam, sensor trip, operator absent, brief pauses <5 min | 5–20% Performance loss |
| 4 | Reduced Speed | Performance ↓ | Running below design speed due to wear, fear of breakdowns, poor material | 5–15% Performance loss |
| 5 | Process Defects (Scrap/Rework) | Quality ↓ | Defects during stable production run | 1–5% Quality loss |
| 6 | Reduced Yield (Startup Losses) | Quality ↓ | Defective output during warmup or after changeover | 0.5–3% Quality loss |
OEE Calculation — Worked Example
A packaging machine, single shift:
| Parameter | Value |
|---|---|
| Planned production time | 480 min (8-hr shift) |
| Planned breaks/meetings | 30 min |
| Net planned production time | 450 min |
| Unplanned downtime | 45 min (breakdown + changeover) |
| Run time | 405 min |
| Ideal cycle time | 40 sec/unit |
| Total units produced | 500 units |
| Rejected / defective units | 15 units |
This machine is average — Performance at 82.3% is the biggest loss. The machine is running slower than its ideal speed or experiencing minor stops. That's where to focus first.
OEE Benchmarks by Industry
What's considered a good OEE varies by industry. Use these benchmarks to assess your performance in context:
| Industry | Typical OEE Range | World Class Target | Main Challenge |
|---|---|---|---|
| Discrete Manufacturing (auto, engineering) | 55–75% | 85%+ | Changeover time, minor stops |
| Packaging | 50–70% | 80%+ | Frequent changeovers, film jams |
| Pharmaceutical | 40–65% | 75%+ | Regulatory changeovers, cleaning |
| Food & Beverage | 50–70% | 80%+ | Sanitation downtime, allergen changeovers |
| Textile | 55–75% | 82%+ | Thread breaks, speed losses |
| Process Industry (chemicals, refining) | 65–80% | 88%+ | Planned maintenance, yield losses |
| Semiconductor / Electronics | 60–75% | 90%+ | Quality yield, equipment precision |
| Plastics / Injection Moulding | 55–72% | 82%+ | Mould changeovers, startup scrap |
Frequently Asked Questions
📦 Embed this calculator on your site
Free for any blog, forum or LinkedIn post. Copy this snippet and paste it where you want the calculator to appear. Attribution to Anedya Enterprise is included automatically.